Yates Anderson

Developer Turnover Litigation: Construction Defect Claims by Associations

The moment control of a condominium or HOA passes from the developer to the unit owners is among the most litigation-prone transitions in community association law — and associations that miss the pre-suit procedural…

The moment control of a condominium or HOA passes from the developer to the unit owners is among the most litigation-prone transitions in community association law — and associations that miss the pre-suit procedural window or the statute of repose may forfeit substantial recoveries.


Doctrinal Framing

Developer turnover — the transfer of board control from the developer (who appointed the initial board) to owners elected by the membership — is a structural inflection point in every common-interest community's history. It is also the moment when the association's construction-defect investigation clock begins running most urgently. The developer has typically maintained control long enough to have run out the initial warranty period for cosmetically obvious defects. The association that takes over often inherits a portfolio of latent defects — in roofing, waterproofing, structural systems, or mechanical elements — that are discoverable only through professional inspection.

Two distinct procedural regimes govern construction-defect claims in the jurisdictions most commonly handled by this firm: Florida's mandatory pre-suit notice process under Chapter 558 and warranty framework under § 718.203, and Alabama's statute of repose framework under §§ 6-5-218 and 6-5-221, read alongside the Right to Cure provisions of Article 13A. Both regimes impose sequenced procedural requirements that must be satisfied before litigation is available, and both contain statutes of repose that can extinguish claims regardless of when the defect becomes discoverable.


Florida: The Chapter 558 Pre-Suit Notice Requirement

Florida Statute § 558.001 states the legislature's intent: construction defect disputes should be resolved through an alternative process of notice, inspection, and confidential settlement negotiations before resort to litigation. The framework in § 558.004 is mandatory, not optional.

Notice Period

Before filing any construction defect action in Florida, the claimant must serve written notice of claim on the contractor, subcontractor, supplier, or design professional at least:

  • 60 days before filing, for most claimants; or
  • 120 days before filing for an association representing more than 20 parcels.

Most condominium and HOA construction-defect cases fall in the 120-day category. The notice must describe in reasonable detail the nature of each alleged defect and, if known, the resulting damage or loss. The claimant must identify the location of each defect sufficiently to enable the respondent to locate it without undue burden. No destructive testing obligation exists at the notice stage.

Inspection and Response

After receiving notice, the respondent has 30 days (50 days for large associations) to inspect the property. The respondent then has an additional period to offer to repair, offer to pay, or deny the claim. If the respondent makes a written offer of repair or payment, the claimant must evaluate the offer. The Act provides a structure for rejected offers that creates consequences in subsequent litigation.

Key limitation: Under § 558.004(1)(d), service of the Chapter 558 notice does not toll any statute of repose period under Chapter 95. This means the 120-day pre-suit notice period must be initiated before — not in lieu of — the expiration of the applicable statute of repose.


Florida: Statutory Warranties Under § 718.203

Florida Statute § 718.203 creates an implied warranty framework for condominium construction. Developers are deemed to have granted the following implied warranties:

  • For each unit: A 3-year warranty for fitness and merchantability commencing with the completion of the building containing the unit.
  • For all other improvements for unit owner use: A 3-year warranty from the date of completion of those improvements.
  • For the roof, structural components, and mechanical, electrical, and plumbing elements serving improvements or a building (except mechanical elements serving only one unit): a warranty beginning with completion of construction of each building and continuing for 3 years or 1 year after owners other than the developer obtain control of the association, whichever occurs last, but in no event more than 5 years.

The last category is the most significant for post-turnover litigation. The "later of 3 years from completion or 1 year from owner control" provision means that where the developer retains control for several years after completion, the warranty may extend well beyond the standard 3-year period — up to a 5-year maximum. Practitioners should calculate both running periods for each building component.

Contractors, subcontractors, and suppliers also grant implied warranties of fitness under § 718.203(2): 3 years for structural components and mechanical elements, 1 year for all other improvements and materials. These warranties run to both the developer and the purchaser of each unit, and they inure to successor owners.


Florida: Statute of Repose — § 95.11(3)(b)

Florida Statute § 95.11(3)(b) governs actions founded on the design, planning, or construction of an improvement to real property:

  • The limitations period is 4 years from the date the authority having jurisdiction issues a certificate of occupancy (CO), certificate of completion, or the date of abandonment of construction, whichever is earliest;
  • For latent defects, the time runs from when the defect is discovered or should have been discovered with the exercise of due diligence;
  • In all events, the action must be commenced within 7 years of the CO/certificate date — this is the statute of repose. After 7 years, no action may be brought regardless of when the defect was discovered, except in cases of fraudulent concealment.

The 7-year repose does not run from the date of turnover or the date of discovery — it runs from the date the authority issued the CO or comparable authorization. For an association that turns over several years after completion, the repose may be well along before the association's professional inspections even begin. This creates urgency in the post-turnover investigation: retain inspectors immediately, document defects, and commence the Chapter 558 pre-suit process before the 7-year clock expires.

Note: The task brief cited § 95.11(3)(c) as the repose provision. Section 95.11(3)(c) governs "an action to recover public money or property held by a public officer" — it is a different provision. The construction-defect statute of repose (4-year limitations / 7-year repose for improvements to real property) is in § 95.11(3)(b), which has been verified and is the correct provision.


Alabama: The § 6-5-218 Statute of Repose

Alabama Code § 6-5-218 is the general Alabama statute of repose for construction defect claims. It bars any action in tort, contract, or otherwise against any person performing or furnishing the design, planning, supervision, or observation of construction or the construction of an improvement to real property more than 7 years after the substantial completion of the improvement. The bar applies to:

  • Deficiencies in design, planning, supervision, or construction;
  • Injury to real or personal property caused by such deficiencies;
  • Personal injury or wrongful death caused by such deficiencies.

The prohibition extends to direct actions and to contribution, indemnity, and third-party claims.

Exception for possessors. The § 6-5-218 bar does not apply as a defense for persons in actual possession or control as owner, tenant, or otherwise of the improvement. Developers who retain ownership of portions of a project — unsold units or unreleased common elements — may not invoke the repose for their ownership period.


Alabama: Article 13A — Actions Against Architects, Contractors, and Engineers

Alabama Code §§ 6-5-220 to 6-5-228 (Article 13A) provides a separate statute of repose applicable specifically to architects, engineers, and licensed general contractors — defined terms under § 6-5-220.

Section 6-5-221 imposes a 7-year bar from substantial completion of construction against architects, engineers, and builders as defined in the article. The section's application depends on the defendant's status at the time: if the architect, engineer, or builder was in actual possession or control of the improvement when the cause of action arose, the repose does not apply to that person for that period of ownership.

Section 6-5-222 addresses the statute of limitations, and § 6-5-225 provides the specific time for commencement of action, typically linking back to the discovery of the defect (for latent defects) or to substantial completion (for patent defects).

The practical effect: Alabama has two overlapping construction-repose regimes — § 6-5-218 for any person involved in construction (broadly), and Article 13A specifically for licensed architects, engineers, and general contractors. Both impose 7-year repose periods running from substantial completion.

Note on "Right to Cure." The task brief referenced the "Alabama Builder's Right to Cure Act" at § 6-5-220 et seq. Section 6-5-220 contains the definitions for Article 13A; there is no separate "Right to Cure Act" at that citation in the Alabama Code. Alabama does not appear to have enacted a separate right-to-repair/cure statute comparable to Florida's Chapter 558. Construction-defect litigation in Alabama proceeds under the standard civil rules after satisfying any contractual pre-suit dispute resolution provisions.


Standing of Associations to Sue

A threshold issue in post-turnover construction-defect litigation is whether the association has standing to sue on behalf of its members. Both Florida and Alabama recognize that associations have standing:

Florida. Section 718.111(3)(b) expressly authorizes a condominium association — after unit owners other than the developer obtain control — to institute, maintain, settle, or appeal actions in its name on behalf of all unit owners concerning matters of common interest, including the roof, structural components, and mechanical elements of the buildings. HOA associations have parallel authority under § 720.303(1). The association acts in a quasi-representative capacity; it does not need to name each individual unit owner as a plaintiff for claims involving common elements.

Alabama. Section 35-8A-302(a)(4) of the Alabama Uniform Condominium Act grants the association authority to "institute, defend, or intervene in litigation or administrative proceedings in its own name on behalf of itself or two or more unit owners on matters affecting the condominium." This provision gives Chapter 8A associations broad litigation authority. For HOAs under the HOA Act, § 35-20-1 et seq. is less specific, but general nonprofit corporation law and the declaration typically authorize the association to sue on behalf of the community.


Causes of Action in Developer Turnover Litigation

Breach of Implied Warranty

The implied warranty of fitness and merchantability under § 718.203 (Florida) and the common law of Alabama gives the association an independent cause of action for construction defects without requiring proof of negligence. The warranty theory is typically preferable where the defect is documented but tracing it to a specific design decision or installation error is difficult.

Negligence

A claim against the developer, general contractor, or design professional for negligent design or construction requires proof of duty, breach, causation, and damages in the standard formulation. The duty element in construction defect cases is ordinarily established by the construction contract and professional standard of care. Expert testimony on both the defect and the standard of care is essential.

Breach of Statutory Warranty (Florida)

Florida's § 718.203 is both an implied warranty provision and a statutory one. The statutory warranty claim runs directly from the statute without requiring proof of the contractual relationship that a common-law implied warranty claim might require. Associations should plead both theories.

Breach of Contract / Breach of Developer Obligations Under the Declaration

In many turnover cases, the association's contract claims against the developer flow from the developer's obligations in the declaration itself — for example, developer representations about common element quality, maintenance standards, or reserve funding. These claims require careful review of the declaration's language.


Practice Notes: Post-Turnover Investigation Protocol

For association counsel:

  1. Retain professional inspectors within 30 days of turnover. The 7-year repose runs from substantial completion — not from turnover. An association that waits two years to investigate may find that the repose bars some or all claims.
  2. Preserve all developer-furnished documents. Section 718.301(4) of the Florida condominium statute requires the developer to deliver plans, permits, warranties, and other specified documents at turnover. Document what was delivered and what was missing.
  3. Commence Chapter 558 notice before the repose expires. The 120-day notice period must be initiated while the claim is still viable. A 558 notice served after the 7-year repose has run does not revive the claim.
  4. Evaluate individual unit owner claims separately. The association's standing covers common elements; individual unit owners may have separate claims for defects in their units that the association cannot assert.

For defendants' counsel and boards contemplating turnover:

  1. Document the turnover inspection record. An association-initiated inspection at turnover, with documented findings, establishes the baseline condition of the property and can limit retrospective claims.
  2. Review the developer's insurance. Developers routinely obtain a certificate of occupancy, sell out, and dissolve the development entity. Pre-turnover investigation of the developer's insurance coverage — particularly completed operations coverage on the builder's CGL policy — may identify an insurance asset even if the developer entity is defunct.

Closing

Developer turnover construction-defect litigation compresses the association's entire warranty and investigation window into the post-turnover years while the repose clock has already been running since substantial completion. The practitioner who takes over a newly turned community association must treat the statute of repose as a hard deadline that cannot be tolled, plan the inspection and pre-suit notice process accordingly, and preserve every remediation record and developer warranty document that the turnover package should have included.


Talk to Yates Anderson

If you are litigating a matter in this area — or weighing whether to — the working analysis above only goes so far. Request a case evaluation and a Yates Anderson attorney will respond within one business day.


Informational only. Not legal advice. No attorney-client relationship is created by reading this post. Consult a licensed attorney in your jurisdiction.

← Back to the Library